Trialling of the Draft Hydropower Sustainability Assessment Protocol

Trialling of the Draft Hydropower Sustainability Assessment Protocol (the 'Draft Protocol') took place from September to December 2009, following the public release of the Draft Protocol in August 2009. The primary objectives was to validate the Forum’s work so far, by providing feedback on how well the Draft Protocol is measuring sustainability, and to inform the final revision.

Trials were primarily conducted by hydropower project developers, owners, and operators from amongst the IHA membership. Trials were often observed or in some cases conducted by Forum members. Project owners were also encouraged to participate in trialling through project self-assessments, or assessments involving invited external experts and partners.

More than 30 trials of the Draft Protocol were identified to be undertaken during this period across North and South America, Africa, Europe, India, China, Southeast Asia and Australia. By the close of the trial period, reports were submitted for 20 trials, covering six continents and 16 countries. Additional trials are known to have been undertaken, the experience of which has undoubtedly enriched the consultation feedback on the Draft Protocol, but the Forum did not receive any formal documentation of these trials.

The table below provides a summary of the trials undertaken for which reports were received and have been included in the Trialling Outcomes Report.

To view a specific trialling report, please click on the relevant project name.

Country

Project Name

Size (MW)

Protocol Sections

Australia

Upper Lake Margaret

8.4

III

Australia

Lower Lake Margaret

3.2

II

Brazil

Sinop

460

I,II

Brazil

São Salvador

243

III

Brazil

Xanxere

21

I

Chile

Aysén Hydroelectic Power Project

2,750

II

China

Shuibuya

1,840

IV

Canada

Wuskwatim

200

II,III

Canada

Keeyask

695

II

Colombia

Sogamoso

820

III

Germany

Waldeck I

70

III

Ghana

Akosombo

1,020

IV

Iceland

Karahnukar

690

Partial
II, III, IV

India

Teesta V

510

IV

Lao PDR

Nam Theun II

1,070

III

Lao PDR, Cambodia, Thailand, Vietnam

3S Basin

n/a

I

South Africa

Palmiet

200

IV

South Africa

Drakensberg

250

IV

South Africa

Ingula

1,332

III

Zambia

Itezhi-tezhi

120

IV