Close
REGION profile

Hydropower in South America

In several countries in South America, hydropower provides more than half of total electricity supply and it is expected to remain the region’s largest renewable source for years to come.
Generation by hydropower (2024)
725TWh
Hydropower installed capacity (2024)
183 GW
Capacity added (2024)
306 MW
Pumped storage installed capacity (2024)
994 MW
Pumped storage capacity added (2024)
0 MW

South America regional overview and outlook

Hydropower is vital for South America’s energy mix, and thanks to natural resources such as the Andes mountains and the Amazon basin, potential for generation is vast. A mere 30% of the region’s hydropower potential is currently being exploited, but even that satisfies approximately 45% of the continent’s electricity demand.

The industry is rising to the challenge as sustainability becomes increasingly important in such an ecologically-sensitive environment. In January 2025, for example, Brazil’s Mascarenhas hydropower plant received gold certification under the Hydropower Sustainability Standard. The 198MW run-of-river plant owned by ENRG became only the second project in South America to achieve gold status, a fitting way to celebrate 50 years in service. Meanwhile, Colombia’s 19.9MW Chorreritas project earned Hydropower Sustainability Standard silver certification, making it only the 10th project in the world to achieve silver or higher. Likewise, the 2,400MW Ituango Hydroelectric Project in Colombia – South America’s largest ongoing hydropower scheme – has only recently begun phased commissioning amid significant technical and social challenges, yet its full capacity will be critical for the country’s energy security once all turbines are online.

By 2024, solar and wind power accounted for 36.8GW of installed capacity in the continent’s grid, out of a total capacity of around 400GW. Renewables may be increasing, but so is potential grid instability as operators attempt to match inconsistent renewable generation with demand.

In response, South America is pioneering hybrid systems combining hydropower and other renewables to maximise sustainability and efficiency. The deployment of PV arrays on hydro reservoir surfaces is a leading example of this approach.

Brazil, for example, began construction of the country’s largest floating solar plant in late 2024. The 54MW facility at the Lajeado hydro reservoir in Tocantins features thousands of solar panels on the dam’s reservoir, leveraging existing transmission while the cooling effect of the water will boost solar output.

Conversely, prospects for rising energy demand are materialising through billion-dollar investments across the region in data centres, extensive mining operations, mega-port logistics hubs and heavy industry. Moreover, the 2024 inauguration of Peru’s Chancay Port – now South America’s largest – has quickly become one of the most energy-intensive and industry-stimulating developments in recent years. Global tech companies are considering Colombia for new regional data centres, and Equinix is leading plans to develop an integrated financial data centre spanning Chile, Colombia and Peru. These trends underscore the urgent need for both reliable baseload generation and flexible, sustainable capacity.

Hydropower remains the backbone of South America’s energy system, and as the region embraces innovation and sustainability – through certified projects and hybrid systems such as floating solar – its vast Andean-Amazon potential continues to shape a resilient, renewable future.

Cachoeira Caldeirão hydropower project, Brazil. Credit: Engie

South America policy and market overview

Although several high-profile projects are reaching completion, the overall rate of hydropower development in South America has plateaued. Regulatory reforms in the sector are often lagging the needs of the industry. Uncertainty around concession renewals, particularly in Brazil, has created challenges for operators, worsened by political volatility and frequent policy shifts in countries such as Argentina and Colombia. This instability has led to investor/state disputes and project delays.

In 2024-2025, Colombia’s government clashed with hydropower companies over alleged opaque pricing and excessive profits, contributing to a 25% drop in investment confidence. In response, authorities are pushing for stricter oversight and tariff reforms.

Sustainable hydropower in South America faces persistent barriers – chiefly slow, multi-layered approval processes and fragmented water-rights regimes. In Argentina, dual federal-and-provincial concessions and lengthy disputes prompted a 2024 provincial water law and audits to ease delays. In Peru, bureaucratic inertia and local opposition have repeatedly slowed hydropower developments. In Chile, the 2022 Water Code reform replaced perpetual water rights with 30-year conditional concessions – curbing speculation in the secondary market by making unused entitlements forfeitable.

Similarly, social and environmental review processes can extend timelines. Colombia, where hydropower still provides about 65% of electricity, has begun issuing decrees to streamline bureaucratic steps and strengthen social consent for new dams.

Meanwhile, Chinese investors are recalibrating their approach. Under China’s Going Out strategy and Belt & Road Initiative, investment initially focused in some markets on constructing large dams. Today, there is greater emphasis on acquiring operational assets such as hydropower plants and transmission companies to secure stable returns and avoid political risk. Firms such as State Grid Corporation of China have expanded into Chilean, Brazilian and Peruvian grids. However, fluctuations in Chinese capital flows, driven by domestic challenges, could impact future funding.

Despite efforts, hydropower faces competition from quicker, lower-risk solar and wind projects. Large projects such as Brazil’s São Luiz do Tapajós dam have stalled due to financing and environmental hurdles or specific issues around indigenous rights.

Climate change poses major risks. Severe droughts intensified by El Niño in 2024 and 2025 critically impaired hydropower generation, leading to power cuts and higher electricity costs. Governments are now urgently seeking to diversify energy sources and improve water management.

Santo Antônio do Jari hydropower project, Brazil. Credit: Engie

Latest developments

Afghanistan
Angola
Argentina
Armenia
Australia
Austria
Azerbaijan
Bhutan
Bolivia
Brazil
Burundi
Cambodia
Cameroon
Canada
Cape Verde
Chile
China
Colombia
Congo
Costa Rica
Czechia
Côte d’Ivoire
Democratic Republic of the Congo
Dominican Republic
Ecuador
Egypt
El Salvador
Estonia
Eswatini
Ethiopia
Finland
Gabon
Georgia
Germany
Guyana
Iceland
India
Indonesia
Iran
Iraq
Italy
Kazakhstan
Kyrgyzstan
Laos
Laos delete
Latvia
Liberia
Lithuania
Madagascar
Malaysia
Mexico
Morocco
Mozambique
Namibia
Nepal
Norway
Pakistan
Panama
Paraguay
Peru
Philippines
Portugal
Russia
Rwanda
Senegal
Serbia
Singapore
Solomon Islands
Spain
Sri Lanka
Sweden
Tajikistan
Tanzania
Thailand
Uganda
United Kingdom
United States of America
Uruguay
Uzbekistan
Venezuela
Vietnam
Zambia

Afghanistan

Hydropower installed capacity (2024)
468
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
<1
TWh

Afghanistan’s planned 285km Qosh-Tepa canal could divert up to 20% of the Amu Darya’s flow, raising concerns in Uzbekistan and Turkmenistan; and in early 2025 Uzbekistan called for further dialogue. In 2024 heavy rains and snow caused severe flooding, destroying over 250 homes and damaging farmland over an extensive area.

Angola

Hydropower installed capacity (2024)
3,890
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
13
TWh

Angola’s Luachimo hydropower station has been modernised and expanded from 8.8MW to 34MW. Commissioned in May 2024, the upgrade included four 8.5MW turbines, a diversion canal and new electrical infrastructure. The US$212 million project was led by China Gezhouba Group, which is also constructing the 2,172MW Caculo Cabaça plant, expected to be commissioned in 2026.

Argentina

Hydropower installed capacity (2024)
11,137
MW
Pumped storage installed capacity (2024)
974
MW
Generation by hydropower (2024)
33
TWh

The Argentinian hydropower sector is undergoing major growth, with several large-scale projects nearing completion and new developments planned. Projects include the 1,310MW Santa Cruz hydroelectric plant, which is slated for completion by 2026. The 950MW Condor Cliff Dam, developed by Represas Patagonia, is set for commissioning by 2027, while the 871MW Chihuido project, still in permitting, is expected online by 2029. The national government also announced plans for the ambitious 3,500MW Cospues plant, aiming for 2033 operations. Meanwhile, the Río Grande PSH, the continent’s largest reversible facility, is operating at 50% capacity, with ongoing renovations due for completion in late 2025.

Argentina’s national hydroelectric capacity was revised down by 746MW in 2024, following a reclassification of the Yacyretá plant to reflect only the Argentine share. Across the country, hydropower generation declined 15.02% compared to 2023, with a further 34.3% drop in January 2025 due to extremely low river inflows. At the same time, large mining endeavours – such as copper and lithium extraction at the Caucharí-Olaroz plant in Jujuy – together with emerging green hydrogen production and the reactivation of petrochemical complexes, will each demand tens or even hundreds of megawatts, have further strained the national energy supply.

Armenia

Hydropower installed capacity (2024)
1,368
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
2
TWh

Armenia reported year-on-year growth in small hydropower in 2024, reaching 190 plants with a combined capacity of 402MW. An additional 59MW is under construction. Overall electricity generation rose by 6.5%, with hydropower contributing to the increase.

Australia

Hydropower installed capacity (2024)
8,827
MW
Pumped storage installed capacity (2024)
2,712
MW
Generation by hydropower (2024)
14
TWh

Australia continues to integrate hydropower, particularly PSH, into its energy transition strategy, with the goal of reaching 82% renewables by 2030. The 2,000MW Borumba project has seen its cost rise from A$14bn (US$9bn) to A$18.4bn (US$11.8bn), prompting a review of its scale and a revised completion date of 2033. Private investment is growing, including a proposed 1.6GW PSH project using WaterNSW reservoirs. Meanwhile, Upper Hunter Hydro is exploring projects at Glenbawn and Glennies Creek; Glenbawn is planned at 770MW/7.7GWh (10-hour duration). The Snowy Hydro 2.0 PSH project continues, with completion delayed to 2028. Permitting is being streamlined, and the A$5bn (US$3.2bn) HumeLink transmission line is due to begin in 2025 to support grid integration.

Austria

Hydropower installed capacity (2024)
11,939
MW
Pumped storage installed capacity (2024)
3,512
MW
Generation by hydropower (2024)
49
TWh

Austria remains one of Europe’s most active countries in PSH expansion and hydropower fleet modernisation, with more than 1.4GW currently under construction. The Kaprun 2029 project, for example, launched by Verbund, involves the modernisation of the Kaprun Main Stage power plant. This includes the reconstruction of the pressure tunnel and key electromechanical equipment. The tunnel boring work began in February 2025. The group has also announced the intention to develop a new PSH plant, Schaufelberg, with an installed capacity of 480MW.

Azerbaijan

Hydropower installed capacity (2024)
1,329
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
3
TWh

In 2024, Azerbaijan hosted COP29 with a focus on climate finance. Ahead of the summit, the government signed a memorandum of understanding with two Chinese companies to support the development of PSH and high-voltage transmission infrastructure.

Bhutan

Hydropower installed capacity (2024)
3,472
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
11
TWh

In 2024, Bhutan’s Electricity Regulatory Authority released its Strategic Plan and licensed the 118MW Nikachhu project. The first two turbines at the delayed 1,020MW Punatsangchhu II project came online in July 2024. Bhutan is also developing a US$830 million climate investment adaptation plan. Bhutan confirmed the European Investment Bank would provide €150 million in loans for 310MW at hydropower and solar projects, alongside ongoing dialogue with the World Bank to address a $600 million finance gap for Bhutan’s hydropower projects.

Bolivia

Hydropower installed capacity (2024)
759
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
4
TWh

Bolivia’s hydropower sector is growing significantly, with major projects including Rio Madera, Ivirizu and Miguillas moving forward. The 3,000MW Rio Madera hydropower project, developed by Eletrobras Participações and Empresa Nacional de Electricidad Bolivia has completed initial site selection and should start on a feasibility study and environmental licensing soon. Commissioning could be as early as 2031. Located on the Madera River in Pando, the project is expected to generate 20TWh of electricity annually. Meanwhile, the Ivirizu complex, which will generate 1.16TWh and the first stage of the 203MW Miguillas hydroelectric plant, developed by ENDE, are both expected to be finalised in 2025.

Brazil

Hydropower installed capacity (2024)
109,982
MW
Pumped storage installed capacity (2024)
20
MW
Generation by hydropower (2024)
415
TWh

A severe dry spell in late 2024 reduced Brazil’s hydropower output to three-year lows, with hydropower falling to a 50% share of the energy mix during September. Anticipation of low water flows in the future has been a factor in limiting development of new sites. The country added a record 10.85GW of total generating capacity during 2024, but hydropower’s contribution to this was small: only 56MW from eleven new projects. The nation’s installed hydropower capacity now stands at 110GW, with 1.3GW more licensed or under construction.

There are currently 32 advanced-stage projects totalling 442MW and 60 licensed projects awaiting construction, representing 945MW. In March 2025, Aneel approved a regulatory change at the Jirau project so that the water level is at 90 metres year-round. This will increase output by an average of 250MW. Meanwhile, Norte Energia, operator of Belo Monte (11,233MW), boosted ESG initiatives, focusing on reforestation, gender diversity, R&D in electric mobility, and indigenous bioeconomy ventures. Meanwhile, large-scale investments in mining and heavy industry – particularly mineral processing, petrochemicals and high-tech manufacturing – alongside growing foreign direct investment in data centres (2025 saw Equinix join Google, AWS and other major operators) are driving urban electricity demand ever higher.

Brazil is also promoting capacity expansion at existing hydropower plants, as the high volume of solar and wind generation is requiring additional dispatchable capacity to provide reliability to the grid. However, current regulations do not give adequate signals to owners to add flexibility when investing in this expansion, which is a missed opportunity that should be addressed by the regulators.

Brazil is now discussing the implementation of new regulatory framework to allow pumped storage hydropower to be developed in the country, taking advantage of the country’s existing supply chain and providing a sustainable solution for the National Grid’s growing needs. 

Burundi

Hydropower installed capacity (2024)
119
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
<1
TWh

Private finance has been secured for two small hydropower projects in Burundi – Upper Ruvyironza (1.65MW) and Upper Mulembwe (9MW) – which will increase national generation capacity by 10%. Backed by a US$35 million loan from the Trade and Development Bank, the projects will generate more than 62GWh annually. Songa Energy is developing both under Burundi’s public-private partnership framework.

Cambodia

Hydropower installed capacity (2024)
1,796
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
7
TWh

In October 2024, Cambodia announced plans to increase its power import capacity by more than 50% over two years, targeting more than 600MW from neighbouring countries including Laos and Thailand. The initiative forms part of a broader strategy to strengthen regional interconnection and grid stability in response to variable hydropower output linked to climate conditions.

Cameroon

Hydropower installed capacity (2024)
1,114
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
6
TWh

The country fully commissioned its 420MW Nachtigal run-of-river project in March 2025, boosting national supply by 30%. Developed by a five-member consortium headed by EDF, the plant will provide baseload power for 35 years. The 30MW Lom-Pangar project was also completed in 2024. Construction of the 500MW Kikot-Mbébé scheme is scheduled to begin in 2026.

Canada

Hydropower installed capacity (2024)
84,300
MW
Pumped storage installed capacity (2024)
177
MW
Generation by hydropower (2024)
342
TWh

Hydropower continues to produce almost 60% of Canada’s total annual electricity generation and represents more than half of its total installed capacity. In several provinces where hydropower is abundant, further expansion is seen as key to satisfying increasing energy needs.

For example, the premiers of Québec and Newfoundland & Labrador recently announced an historic agreement to collaborate on future electricity development through joint ventures. The deal includes increased hydropower generation capacity at the existing Churchill Falls facility, the development of a new generation station on the Churchill Falls site, and a new facility at Gull Island. These projects will add a total of 3,900MW new hydropower generation capacity.

In addition, Newfoundland & Labrador Hydro’s 2024 Resource Adequacy Plan reveals that a new 154MW hydroelectric unit for its Bay d’Espoir facility is a frontrunner among several supply options.

In British Columbia, a major milestone was achieved at the Site C project with the successful testing and commissioning of the first two of its six generating units.

As the third major dam and generating station on the Peace River in northeast BC, Site C is poised to significantly boost the province’s hydroelectric capacity. Once fully operational, it will add 1,100MW of capacity and generate approximately 5.1TWh annually – enough to satisfy approximately 8% of BC’s total electricity needs.

Pumped storage development also took a significant step forward in Nova Scotia, where there are proposals to repurpose a disused mine into a closed-loop pumped hydro energy storage system. A feasibility study will be conducted for the facility which will be complemented by photovoltaic panels.

Ontario also announced investment to advance a PSH project, including the completion of a detailed cost estimate and environmental assessments to determine the feasibility of the project.

The province’s Minister of Energy also initiated the Northern Hydro Program (NHP). The initiative, which is being developed by the Independent Electric System Operator (IESO), aims to recontract existing hydroelectric generation facilities in northern Ontario with an installed capacity greater than 10MW. Eligible facilities will have contracts with the IESO or the Ontario Electricity Financial Corporation (OEFC) that have expired or are set to expire on or before April 30, 2043. The program will also consider factors beyond facilities’ ability to generate electricity, including:

  • The social and regional benefits hydropower provides – including water management, which can help with flood control, irrigation and the support of local ecosystems.
  • The capital investments needed to keep large hydroelectric facilities running safely and efficiently over time.

More than two dozen hydropower facilities are expected to qualify for contracting again under the NHP, highlighting the extent of the program’s impact across northern Ontario.

Several major refurbishment projects have also continued or were announced in BC, Ontario and Québec.

Cape Verde

Hydropower installed capacity (2024)
0
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
0
TWh

A 20MW/160MWh pumped storage project will soon be operational at Chão Gonçalves on Santiago Island, supported by a €60 million loan from the European Investment Bank. Due online in 2028, the plant will help reduce fossil fuel use by 22% and support the national goal of sourcing 54% of electricity from renewables by 2030.

Chile

Hydropower installed capacity (2024)
7,566
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
26
TWh

Chile’s installed generating capacity has grown spectacularly in recent years, driven by variable renewables; hydropower, however, has played a relatively small role in this expansion. In 2024, four projects added a total of 157.7MW to Chile’s hydropower capacity: Los Cóndores (150MW), Pasada Piedras Negras (3MW), La Confianza (2.6MW), and Nueva Ampliación PMGD Las Flores (2.1MW). Four more projects, with a combined investment of $677 million, are also under construction: Las Nieves (6MW), Dos Valles (4.5MW), Los Lagos (48MW) and Central Ñuble de Pasada (136MW). A 52MW Los Lagos run-of-river project has also recently received approval.

China

Hydropower installed capacity (2024)
435,950
MW
Pumped storage installed capacity (2024)
58,690
MW
Generation by hydropower (2024)
1,424
TWh

China remains the global leader of hydropower development, with ongoing growth in both conventional hydropower and PSH. While conventional project development has slowed from previous peaks, notable progress continues. The 1,200MW Yangqu station in Qinghai Province, commissioned in 2024, is part of a cascade along the Yellow River and is expected to produce 4.7TWh annually. Meanwhile, PSH is emerging as China’s primary hydropower growth area. In 2024, the 3.6GW Fengning project in Hebei Province, now the world’s largest PSH facility, was commissioned by State Grid Xinyuan, underscoring China’s emphasis on energy storage and system flexibility.

Colombia

Hydropower installed capacity (2024)
13,218
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
55
TWh

Construction of Ituango, Colombia’s 2,400MW run-of-river project, is progressing. It is the country’s largest and among the continent’s ten biggest hydropower projects. By late 2024, Ituango had partially entered service with 1,200MW installed, and is expected to reach full capacity by 2027. Elsewhere, hydropower development has lagged, with just two projects completed in 2024 – TZ II (10.5MW) and Alejandría (2MW). Both are currently undergoing testing. Two major projects, Porvenir II (352MW) and Miel II (120MW), have been approved, however, signalling future growth for Colombia’s hydropower sector.

Congo

Hydropower installed capacity (2024)
214
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
1
TWh

Construction has begun on the 600–800MW Sounda hydropower plant in Congo, following a memorandum signed with China Overseas Corporation in September 2024. With a US$9.4 billion budget, the project is nearly four times the size of the country’s current installed hydropower capacity. Completion is expected by 2030, significantly expanding national generation potential.  

Costa Rica

Hydropower installed capacity (2024)
2,353
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
8
TWh

Plans were announced to build the 53MW Fourth Cliff hydropower plant, which could be operational by 2031. While still in the pre-feasibility stage, the plant would complement the country’s already impressive fleet and help mitigate energy challenges associated with climate variability and cyclical phenomena such as El Niño, which can affect rainfall and hydropower generation.

Czechia

Hydropower installed capacity (2024)
3,457
MW
Pumped storage installed capacity (2024)
1,172
MW
Generation by hydropower (2024)
4
TWh

Six potential sites for new PSH projects were identified by the Czech Republic’s Ministry of the Environment and Ministry of Agriculture in June 2024. The country is exploring PSH opportunities as it looks to increase storage capacity and the resilience of its power system. The six sites are connected to existing dams, according to the government, therefore construction is unlikely to have significant negative environmental or social impact.

Côte d’Ivoire

Hydropower installed capacity (2024)
992
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
3
TWh

Côte d’Ivoire commissioned the 112.9MW Gribo-Popoli plant in July 2024, part of a planned 508MW cascade on the Sassandra River developed by the state power company, CI-Energies, and built by PowerChina. The 44MW Singrobo-Ahouaty project on the Bandama River is also nearing completion and will supply peak power under the country’s first privately financed hydropower model. Developed by Ivoire Hydro Energy with Themis Group, the project won IJ Global’s Power Deal of the Year and was backed by a €40 million loan from the African Development Bank.

Democratic Republic of the Congo

Hydropower installed capacity (2024)
3,216
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
13
TWh

Two 200MW hydropower projects are progressing in the DRC. On the Lufira River, Kipay Investments SAS and Afreximbank are partnering on technical, legal and financial preparation for the country’s first private renewable energy project. On the Lualaba River, Nzilo II will supply power to China-based mining firm CMOC, complementing solar generation at night. While the 44GW Grand Inga project remains in the planning stage, a US$22.1 million substation upgrade at Inga I and II is already improving grid stability and reducing energy losses.  

Dominican Republic

Hydropower installed capacity (2024)
641
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
1
TWh

Three multipurpose projects incorporating hydropower advanced: Las Placetas (89MW) which includes pumped storage, Gina and Guayubín.

Ecuador

Hydropower installed capacity (2024)
5,419
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
23
TWh

Ecuador’s hydropower system remains under pressure due to droughts, which have triggered electricity blackouts. With 72% of the country’s power generation dependent on water, the government is turning to solar projects to add resilience. The government is also passing laws to help boost private investment in hydropower from 10% to 47%. Other measures include a 12-month zero import tariff for energy generators. Meanwhile, construction has yet to begin on the Zamora hydropower project (3,565MW), the first 68MW turbine in the 254.4MW Toachi-Pilatón project has been completed, and feasibility studies are underway for major projects in the Santiago basin (over 3,000MW) and further Zamora schemes.

Egypt

Hydropower installed capacity (2024)
2,832
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
15
TWh

The Egyptian authorities have completed feasibility studies for two 1,000MW pumped storage projects in Luxor and Qena, with investment expected to reach US$2.5 billion. Both projects would use Nile water and are planned for private-sector development, though a timeline has not been confirmed. Meanwhile, the government is preparing to relaunch the tender process for the 2.4GW Ataqa Mountain PSH project, which uses treated wastewater, after initial financing efforts by Sinohydro were unsuccessful.

El Salvador

Hydropower installed capacity (2024)
639
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
2
TWh

The 3 de Febrero hydropower project (previously known as El Chaparral) completed its first full year of operation, adding 64MW to the energy mix and acting as a giant battery to integrate other renewables. 

Estonia

Hydropower installed capacity (2024)
0
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
<1
TWh

Development of the Paldiski project, Estonia’s first PSH plant, moved a step closer to ground-breaking phase in 2024 as Energiasalv issued a tender for the design and construction of the 500MW underground facility. Construction works were originally expected to begin in Q2 2025 but now depend on the conclusion of the tender process.

Eswatini

Hydropower installed capacity (2024)
60
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
<1
TWh

Construction has begun on Eswatini’s first privately financed hydropower project following financial close in February 2025. The 13.5MW Lower Maguduza project is being developed by African Clean Energy Developments, with African Infrastructure Investment Managers and the Eswatini Public Service Pensions Fund as shareholders. The US$62.4-67.6 million scheme is backed by Standard Bank, with Zutari Eswatini overseeing construction on behalf of the project owners. Construction is expected to take 25 months.

Ethiopia

Hydropower installed capacity (2024)
6,024
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
20
TWh

Ethiopia has commissioned the third and fourth units of the Grand Ethiopian Renaissance Dam in 2024, adding 800MW to the grid. Construction is nearly complete, with full capacity set to reach 5,150MW. Ethiopian Electric Power is also progressing with three major projects – Genale Dawa 5 (100MW), Geba Stage 1 and 2 (371MW), and Halelle Werabesa Stage 1 and 2 (422MW) – with African Development Bank support for technical studies.

Finland

Hydropower installed capacity (2024)
3,190
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
15
TWh

A new and innovative underground PSH project in Pyhäjärvi was announced in May 2024. The project is unique because it reuses decommissioned mine infrastructure, combining underground pumped hydro and battery storage systems. It is designed to deliver 530MWh of energy storage with a peak capacity of 75MW. It will be developed alongside a battery energy storage system of comparable capacity. 

Gabon

Hydropower installed capacity (2024)
331
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
2
TWh

The Kinguélé Aval hydroelectric project in Gabon has secured its initial disbursement of €134 million from various financial institutions. Developed under a public–private partnership by Asonha Energie, majority-owned by Meridiam, and the Gabon Power Company, the 35MW project on the Mbei River has a construction consortium led by Sinohydro, alongside French firms Artelia and EDF. Additionally, Meridiam plans to establish a biodiversity sanctuary, provide electricity to the village of Andock Foula, and support the Kango hospital with essential equipment.

Georgia

Hydropower installed capacity (2024)
3,514
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
11
TWh

The Georgian Economy Ministry has indicated that it is targeting 10GW of electricity generation by 2032 and that the share of hydropower will rise from 50% to 74% by that year. In 2024 the 44.5MW Khobi-2 hydropower project was commissioned, and the 22.4MW Kaspi Hydro Power Plant was announced and is set to be built on the Mtkvari River in the Kaspi Municipality.

Germany

Hydropower installed capacity (2024)
14,561
MW
Pumped storage installed capacity (2024)
9,449
MW
Generation by hydropower (2024)
22
TWh

Construction work to recommission the 160MW pumped storage plant at Happurg is underway, just months after plans were announced by Uniper in mid-2024. The project, with a total expected investment of €250 million, is set to enhance grid flexibility and reliability in southern Germany. The plant is scheduled to be fully operational by 2028.

Guyana

Hydropower installed capacity (2024)
3
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
4
TWh

Guyana has revived its flagship 165MW Amaila Falls hydropower project after years of delays and failed attempts. Initially awarded to China Railway Group under a BOOT model, talks collapsed in 2022 over costs. As of 2024, the government is re-tendering the project, with four international firms prequalified. Amaila is central to Guyana’s low-carbon strategy, with expectations it will supply more than 50% of the nation’s electricity, reducing dependence on oil. A public–private partnership is expected. Key hurdles including financing challenges, indigenous consultation, and environmental concerns remain ahead of the targeted 2029 commissioning date.

Iceland

Hydropower installed capacity (2024)
2,289
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
14
TWh

Tendering of the 95MW Hvammur greenfield HEP is under way and commissioning is expected in 2030. The project will generate 740GWh annually. Tendering of the expansion of the Sigalda project is also ongoing, where one 65MW turbine will be added to increase flexibility, with commissioning expected by end-2028. At the same time stops will be utilised to refurbish the existing 3 x 50MW station and dam. The pipeline of projects is healthy both for greenfield and brownfield expansion developments.

India

Hydropower installed capacity (2024)
52,069
MW
Pumped storage installed capacity (2024)
4,746
MW
Generation by hydropower (2024)
198
TWh

India is rapidly emerging as a global leader in PSH. It aims to add 51GW of PSH by 2032. To support India’s storage targets, the Central Electricity Authority (CEA) has accelerated project approvals for six major projects totalling 7.5GW in 2024/25 and plans to approve at least 13 more projects (22GW) in 2025/26. 

As of early 2025, approximately 44.5GW of pumped storage projects are at various stages of development. Three private players – Greenko, Adani Green, and JSW Energy – are poised to develop nearly two-thirds of the country’s planned 51GW PSH capacity by 2032. Greenko will commission the 1.68GW Pinnapuram project – its first PSH plant – in September 2025, while Adani Green’s 500MW Chitravathi project is slated for commissioning in 2027. Elsewhere in the country:

  • In Madhya Pradesh, construction has begun on the 1.92GW Gandhisagar pumped storage project, with commissioning scheduled for June 2028. The 640MW Indira Sagar project is currently in the early stages of development.
  • In Karnataka, the 2GW Sharavathy pumped storage project is under construction and is expected to be commissioned in December 2029. The 300MW Narihalla project is also in its early development phase.
  • In Odisha, construction has started on the 600MW Upper Indravati project, following detailed project report (DPR) approval. In parallel, preliminary investigation work has commenced for the 500MW Balimela project.
  • In Tamil Nadu, early-stage development is underway for the 1GW Upper Bhavani pumped storage project.
  • In Gujarat, development is progressing on two projects: the 300MW Juni Kayaliwel project and the 300MW Amalpada project. Both projects have signed memoranda of understanding (MoUs).
  • In Uttar Pradesh, the 1.5GW Panaura project has been identified as one of 33 potential pumped storage sites under evaluation in the state.
  • In Maharashtra, construction has begun on the 1GW Bhivpuri and 1.5GW Bhavali projects, following DPR approvals in 2024–25. The 1.5GW Tarali and 1.8GW Shirwata projects are in the early development phase. Additionally, Maharashtra is advancing two 2GW pumped storage projects – Ghosla and Kamod – under a signed MoU with Megha Engineering & Infrastructures Ltd, with both projects expected to be completed by 2030.
  • In Kerala, REC Limited has signed a memorandum of understanding to finance US$2.1 million in the pumped storage sector over the next five years. The state’s Energy Management Centre has identified several viable sites and is conducting pre-feasibility studies, with the most promising projects to be selected for detailed feasibility reports.

In addition to India’s support for PSH, conventional hydropower projects continue to progress, including major works completed on the 2GW Subansiri Lower hydroelectric project. 

Indonesia

Hydropower installed capacity (2024)
6,570
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
25
TWh

Indonesia continues to expand its hydropower sector in alignment with regional energy goals. In February 2025, the government released its updated Electricity Supply Business Plan (RUPTL) for 2025–2034, targeting an increase in renewable energy from 12% to 35% of the national energy mix, including an additional 16GW of hydropower capacity. Multiple projects are scheduled to commence operations in 2025: 

  • Upper Cisokan Pumped Storage Power Plant: Indonesia’s first pumped storage facility (1,040MW), located in West Java. 
  • PLTA Asahan 3 and Jatigede: Part of 37 strategic electricity projects commissioned in January 2025, collectively adding 3.2GW. 
  • PLTA Peusangan and Merangin: Peusangan 1 (45MW) and 2 (43MW) in Aceh, and the 350MW Merangin plant in Jambi. 
  • Batang Toru Hydropower Plant: A 510MW project in North Sumatra delayed by funding and environmental concerns, now expected online in 2025.

Iran

Hydropower installed capacity (2024)
13,295
MW
Pumped storage installed capacity (2024)
1,040
MW
Generation by hydropower (2024)
18
TWh

Iran’s hydropower output increased year-on-year in 2024, supported by strong rainfall and spring run-off that brought many reservoirs to 90% capacity. Sardasht and Darian plants recorded exceptional generation, with Darian exceeding 104% of its previous year’s output by October 2024. By early 2025, spring rains caused Karun 4 and Rudbar Lorestan dams to reach full capacity. Iran’s Minister of Energy called for accelerated pumped storage development, expediting construction of Karun II, upgrades to existing plants at Siah Bisheh, and greater youth engagement in the sector. Four small and medium projects were approved in July 2024, alongside ongoing major electricity market reforms on pricing and market structure.

Iraq

Hydropower installed capacity (2024)
2,816
MW
Pumped storage installed capacity (2024)
240
MW
Generation by hydropower (2024)
1
TWh

Iraq’s President Abdul Latif Rashid called for urgent action on desertification, citing the increasing frequency of droughts and their impact on hydropower assets. He noted that nearly 40% of Iraq’s land is affected, with water resources under severe strain. According to Environment Minister Helo Al-Askari, Iraq is making progress on its climate targets and emphasising a transition to sustainable energy sources, including hydropower.

Italy

Hydropower installed capacity (2024)
22,089
MW
Pumped storage installed capacity (2024)
7,256
MW
Generation by hydropower (2024)
46
TWh

Activity in Italy’s pumped storage market is intensifying as the country prepares to integrate large volumes of variable renewable energy into a relatively fragmented power system. Several pumped storage projects are currently being developed with the goal of securing contracts in the soon-to-be-launched capacity market (MACSE). For example, in April 2024, Repower confirmed that its 600MW Campolattaro PSH project was awaiting final permitting approval. Just months later, in July, Edison and WeBuild announced plans to jointly develop the Pescopagano and Villarosa PSH projects, with a combined capacity of 500MW.

Kazakhstan

Hydropower installed capacity (2024)
3,146
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
11
TWh

At the start of 2024, Kazakhstan announced plans to add 26GW of new generating capacity, including 600MW of hydropower by 2027–28. A national programme to modernise energy and communal infrastructure was also approved. Renewable electricity output, including small hydropower, increased into early 2025. In November 2024, 200MW of small hydropower was procured through auctions (7.3¢/kWh) followed by a second auction for 100MW at competitive pricing.

Kyrgyzstan

Hydropower installed capacity (2024)
4,067
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
14
TWh

In 2024, Kyrgyzstan marked 50 years of Toktogul, the country’s largest hydropower plant, which is now undergoing upgrades to increase capacity from 1.32GW to 1.38GW and extend its lifespan by 30 years. President Japarov inaugurated the 25MW Bala-Saruu plant which was completed in three years. A 1,305MW Suusamyr-Kokomeren cascade was announced in partnership with the China National Electric Engineering Co. The World Bank approved $13.6 million to update feasibility and environmental plans for Kambarata-1.

Kyrgyzstan’s government announced in 2024 that small hydropower will reach 405MW by 2027, with 18 new plants to be commissioned in 2025. Kulanak HPP (100MW) is due to be commissioned in 2026, and Kambarata-2 began early commissioning in 2025.

Laos

Hydropower installed capacity (2024)
9,760
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
40
TWh

Laos has emerged as a regional hub for hydropower development in South East Asia, with strong investment flows and export-driven policies. The country is targeting 13GW of capacity by 2030, up from 9GW in 2020. With an estimated potential of 26GW, expansion is ongoing. Over 4,000MW is under construction, including Pak Beng (912MW) and Pak Lay (770MW), while more than 6,000MW is under feasibility review, largely along the Mekong River. Strong investment from China, Thailand and Vietnam continues to drive growth, supporting both domestic supply and electricity exports.

Laos delete

Hydropower installed capacity (2024)
MW
Pumped storage installed capacity (2024)
MW
Generation by hydropower (2024)
TWh

Latvia

Hydropower installed capacity (2024)
1,558
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
3
TWh

Modernisation of Latvia’s hydropower plants on the Daugava River is set to progress following a €230 million loan issued by the Nordic Investment Bank to Latvenergo. Part of this investment will be used to increase plant efficiency, with the goal of ramping up hydropower production across the country.

Liberia

Hydropower installed capacity (2024)
93
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
<1
TWh

The World Bank has approved US$45 million for Liberia’s Renewable Energy Solar Power Intervention Project (RESPITE), which will expand Mount Coffee hydropower plant from 88MW to 129MW and fund a 20MW solar facility – Liberia’s first utility-scale solar project. A feasibility study is also underway for a potential 150MW hydropower plant upstream on the St Paul River.

Lithuania

Hydropower installed capacity (2024)
1,029
MW
Pumped storage installed capacity (2024)
900
MW
Generation by hydropower (2024)
<1
TWh

Expansion of the Kruonis pumped storage plant in Lithuania is set to proceed following approval of a €105 million loan from the European Investment Bank. The funding will support construction of a fifth generating unit, which will add 110MW of capacity to the facility. Once complete, the new unit is expected to enhance grid stability, contribute to energy infrastructure modernisation and further support Lithuania’s transition to renewable energy.

Madagascar

Hydropower installed capacity (2024)
189
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
<1
TWh

Agreement has been reached on the 120MW Volobe II run-of-river project, clearing the way for financial close and construction. The €350 million plant will increase national generation capacity by approximately 20% and deliver 750GWh annually. Developed by CGHV – a consortium including Jovena, Scatec, Africa50 and Colas –Volobe II is expected to begin operation in 2028, subject to construction timelines.

Malaysia

Hydropower installed capacity (2024)
6,297
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
32
TWh

As ASEAN chair from January 2025, Malaysia is prioritising cross-border electricity trade from clean sources such as hydropower, solar and wind to strengthen regional energy security and sustainability. The country continues to advance its renewable energy strategy through policy initiatives and project development, with several hydropower projects moving towards commissioning. 

  • Sarawak’s hydropower developments: Sarawak Energy is progressing major schemes, including the 1,285MW Baleh Hydroelectric Plant, expected to begin operations by 2029/2030. 
  • Tenaga Nasional Berhad (TNB) projects: TNB is developing the 300MW Nenggiri Hydroelectric Plant in Kelantan, targeting operation by 2027. 
  • Floating solar initiatives: In December 2024, Sarawak commissioned a 50MW floating solar project, co-owned with an independent power producer (IPP and Sarawak Energy), marking progress in solar-grid integration.

Mexico

Hydropower installed capacity (2024)
12,614
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
23
TWh

Efforts to modernise existing hydropower plants continued in Mexico, including capacity additions where feasible.

Morocco

Hydropower installed capacity (2024)
2,585
MW
Pumped storage installed capacity (2024)
814
MW
Generation by hydropower (2024)
1
TWh

The El Menzel PSH plant near Séfrou is one of the most significant projects in Africa’s pipeline. It is expected to enter commercial operation by the end of 2028, adding 300MW to the grid. The project will enhance the country's clean energy transition by integrating renewable energy sources, improving grid stability, and meeting peak electricity demand, with co-financing secured from the Islamic Development Bank.

Mozambique

Hydropower installed capacity (2024)
2,216
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
18
TWh

A draft energy transition strategy suggests authorities are considering 14,000MW of new hydropower in Mozambique, mainly from the Zambezi River, with 9,000MW to be added between 2030 and 2040. The plan builds on Cahora Bassa (2,075MW) and the under-construction 1,500MW Mphanda Nkuwa. It also outlines green industrial development and grid expansion, while controversially proposing to end power exports to South Africa after 2030.

Namibia

Hydropower installed capacity (2024)
347
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
2
TWh

Namibia and Angola have signed an implementation agreement for the 600MW Baynes hydropower project on the Kunene River, which forms the border between the two countries. Output will be shared equally, and the site will also improve grid links between the two countries and support electricity exchange across the Southern African region. The plant is expected to operate during periods of intermediate and peak demand, helping to reduce reliance on costly imports.

Nepal

Hydropower installed capacity (2024)
3,339
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
3
TWh

At the start of 2025, Nepal’s Supreme Court ordered a halt to development activities – including hydropower – within all protected areas. The ruling covers 12 national parks, six conservation areas, one hunting reserve, one wildlife reserve and 13 buffer zones. The Independent Power Producers’ Association of Nepal noted the decision could affect nearly 300 hydropower projects and up to 20GW of potential capacity.

Meanwhile, support for large-scale projects continues. India’s Renewable Energy Development Agency will invest in the 900MW Upper Karnali project, acquiring a 10% stake alongside its partnership with SJVN Limited. US-based BG Titan Group signed an MoU to develop the 650MW Tamakoshi 3 project. The UK’s British International Investment (BII) also agreed a trade loan to support Nepal’s renewable energy and manufacturing sectors, including hydropower.

Norway

Hydropower installed capacity (2024)
33,909
MW
Pumped storage installed capacity (2024)
1,401
MW
Generation by hydropower (2024)
140
TWh

A new Norwegian pumped storage project is set to enter the construction phase following the announcement of a €113 million investment by Hydro in 2024. Full commissioning is expected to begin by 2029. The facility is designed to generate 84GWh of electricity annually by pumping water from the Fivlemyrane reservoir, 1,018m above sea level, to the Illvatn reservoir, which is approximately 350m higher. Storage capacity at Illvatn will be increased by the construction of a new drainage tunnel, allowing for a lower minimum regulated water level. 

Pakistan

Hydropower installed capacity (2024)
10,635
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
40
TWh

Pakistan aims to expand hydropower to 20GW by 2030. In 2024, the 884MW Suki Kinari run-of-river project became fully operational on the Kunhar River under the China–Pakistan Economic Corridor. The World Bank approved US$1 billion for the Dasu project, while encouraging acceleration. The excavation of Dasu’s foundation continued with the aim of completing the 4,320MW asset by 2027. Kuwait Fund for Arab Economic Development announced a loan of US$24 million to support the 800MW Mohmand project. Tarbela’s 5th Extension is set to boost capacity from 4,888MW to 6,418MW by 2026. The 4.2MW Nai Gaj Dam construction began in 2024. Pakistan’s major reservoirs recorded cumulative water storage which surpassed the five-year average in August 2024.

Panama

Hydropower installed capacity (2024)
1,848
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
8
TWh

Construction continued on Bocas del Toro hydropower project (224MW, previously named Changuinola II). Other projects under construction are Burica (63MW) and Chuspa (10MW).

Paraguay

Hydropower installed capacity (2024)
8,810
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
53
TWh

Itaipú Binacional, operators of one of the world’s largest hydropower plants, supplied Paraguay with 20.4TWh of electricity between January and December 2024 – a record for cumulative energy production. During 2024, hydropower supply to Paraguay rose by 4.5% compared to 2023. Sector investment has been focused on optimising existing assets rather than launching new large-scale projects. For example, the 200MW Acaray plant is undergoing major modernisation under a contract awarded to AFRY (working in consortium with Latinoconsult and supported by Inter-American Development Bank funding (IADB)). The goal is to improve capacity and extend the plant’s operational life.

Peru

Hydropower installed capacity (2024)
5,515
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
32
TWh

San Gabán III (209.3MW) is located in Carabaya province, Puno, and is designed to generate approximately 1.25TWh annually. It will bolster supply to Peru's southern grid and support the mining sector. The project is initiated in 2017 and was commissioned in April 2025. Environmental management plans have been implemented to mitigate impacts on nearby protected areas and to benefit local  communities through electrification and employment opportunities. In addition, construction of four small hydropower projects is more than 25% complete – CH Santa Lorenza (19MW), CH Anashironi (20MW), Centauro I (12.5MW), and Centauro II (12MW) – with operation scheduled between 2025 and 2027. Collectively, large-scale projects with a combined value exceeding US$7 billion – encompassing major mining developments, port logistics (notably the Chancay terminal) and heavy-industry installations – will increase the country’s energy demand in the coming years.

Philippines

Hydropower installed capacity (2024)
4,425
MW
Pumped storage installed capacity (2024)
729
MW
Generation by hydropower (2024)
10
TWh

The Philippines is targeting an ambitious 35% renewable energy share by 2030 and 50% by 2040, up from 22.8% in 2022. Recent policies include the auctioning of 300MW of impounding hydro and 4,250MW of PSH projects, which attracted nearly 7GW in pumped storage bids. A US$15 billion agreement with Masdar supports up to 1GW of solar, wind, and battery storage by 2030 and 10GW by 2035. Around 250MW of small hydropower is also planned, contributing to energy diversification and rural electrification.

Portugal

Hydropower installed capacity (2024)
8,352
MW
Pumped storage installed capacity (2024)
3,867
MW
Generation by hydropower (2024)
15
TWh

Commissioning of the Alto Tâmega hydropower plant marks the final stage in the development of Portugal’s large-scale Tâmega Complex. The 160MW plant is located at the base of the Alto Tâmega Dam, a 105-metre-high double-curved vault structure built with 220,000 cubic metres of concrete and spanning 335 metres across its crown. The fully operational Alto Tâmega complex has 1,158MW of installed capacity, including the 880MW Gouvães pumped storage facility and the 118MW Daivões plant.

Russia

Hydropower installed capacity (2024)
54,327
MW
Pumped storage installed capacity (2024)
1,385
MW
Generation by hydropower (2024)
212
TWh

Russia’s hydropower generation rose by 4.9% year-on-year in 2024. In early 2025, however, low snowmelt led to earlier-than-usual filling of the Volga-Karma hydropower cascade, highlighting growing hydrological variability. 

In 2024, the Russian Ministry of Energy unveiled its Energy Strategy to 2050, which was approved in April 2025. The strategy targets a 17% increase in hydropower generation from 2023 levels and includes 7.8GW of new hydro and pumped storage capacity in Siberia and the Far East.

As part of the Unified Electricity System Operator’s plans for grid modernisation through 2042, a new digital system – SPDM – has been introduced to automate hourly balancing and enhance grid reliability. RusHydro’s modernisation programme added 33.5MW of capacity in 2024 across Ust-Srednekanskaya, Ezminskaya, Nizhny Novgorod, Votkinskaya, Saratov, Volzhskaya and Cheboksary. Upgrades are also ongoing at the Uglich, Volzhskaya, Saratov and Nizhny Novgorod hydropower plants.

Rwanda

Hydropower installed capacity (2024)
143
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
<1
TWh

Progress continues on the 206MW Ruzizi III Regional Hydropower Project, which will supply electricity equally to Rwanda, Burundi and the Democratic Republic of Congo. Developed as a public–private partnership, the project aims to finalise agreements with all stakeholders and financiers by September 2025. Construction would then begin, with commissioning scheduled for 2030.

Senegal

Hydropower installed capacity (2024)
81
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
<1
TWh

Construction has commenced on the 128MW Sambangalou hydroelectric project in Senegal, with VINCI overseeing the development alongside other partners. The project includes the construction of a dam and reservoir with a capacity of 4 billion m3, providing water for energy generation, irrigation and drinking. The electricity generated will benefit the Gambia River Basin Development Organisation countries, with VINCI Energies installing high-voltage lines.

Serbia

Hydropower installed capacity (2024)
3,151
MW
Pumped storage installed capacity (2024)
614
MW
Generation by hydropower (2024)
11
TWh

Plans to accelerate Serbia’s decarbonisation and strengthen energy security are due to move forward following the government’s announcement in March 2024 of a €400 million investment package. Backed by the European Union and the European Investment Bank, the funding will support modernisation of four existing hydropower plants and the development of the 2.4GW Bistrica pumped storage project.

Singapore

Hydropower installed capacity (2024)
0
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
0
TWh

Singapore is strengthening its energy strategy by importing regional hydropower and expanding grid infrastructure. It endorsed the COP29 Global Energy Storage and Grids Pledge in December 2024. With 95% of electricity from imported natural gas, improving storage and grids is key to integrating renewables. Under the LTMS-PIP cross-border electricity trading initiative Singapore began importing 100MW of hydropower from Laos in 2022, doubling to 200MW by 2024. It plans to import up to 6GW of low-carbon power by 2035.

Solomon Islands

Hydropower installed capacity (2024)
<1
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
<1
TWh

The Solomon Islands has a 2030 target for nationwide electrification, and yet only around half of the population is currently connected to the national grid. Ongoing projects include the Tina River Hydropower Project, which is 23% complete and aims to provide 78GWh annually from a 15MW plant, meeting nearly 70% of Honiara’s electricity demand by early 2028. Construction of the project’s main dam began in November 2024, marked by a ceremony attended by ADB and government representatives

Spain

Hydropower installed capacity (2024)
22,747
MW
Pumped storage installed capacity (2024)
5,650
MW
Generation by hydropower (2024)
35
TWh

Spain is considering the introduction of a capacity market under its National Energy and Climate Plan, to ensure long-term grid reliability and support the integration of variable renewables. While the mechanism will be open to a range of technologies, several pumped storage projects are already moving forward in parallel, supported by targeted grants and regulatory approvals.

In March 2024, Iberdrola’s Alcántara pumped storage project received a €44.9 million grant from the Institute for Energy Diversification and Saving. The project will deliver 440MW of capacity and 15GWh of storage, with construction expected to begin in 2025 and commercial operation in mid-2030. Iberdrola’s Valdecañas project (275MW / 210GWh) secured administrative approval in July and has already commissioned its first pumping unit. The project uses existing infrastructure and includes a 15MW / 7.5MWh chemical battery to enhance flexibility.

A new partnership between Capital Energy and Verbund Green Power will assess two additional pumped storage plants with a combined capacity of 830MW. Development of the 200MW Salto de Chira project in the Canary Islands is also progressing, supported by a €300 million loan from the European Investment Bank. The facility will include 3.5GWh of storage and be connected to a desalination plant. 

Sri Lanka

Hydropower installed capacity (2024)
2,099
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
7
TWh

The 126MW Uma Oya project was inaugurated in April 2024 by the presidents of Sri Lanka and Iran. It will supply 290GWh annually and support irrigation. Sri Lanka is also progressing with its first 600MW pumped storage project, Maya Oya, as the Ceylon Electricity Board seeks long-term international funding to maintain affordable electricity tariffs for consumers.

Sweden

Hydropower installed capacity (2024)
16,399
MW
Pumped storage installed capacity (2024)
99
MW
Generation by hydropower (2024)
65
TWh

Sweden could significantly boost hydropower capacity and flexibility by upgrading existing plants, according to a recent study by AFRY supported by the Swedish Association of Engineers. The analysis estimates that up to 4GW of additional capacity could be added, which is equal to the output of approximately 3.5 nuclear reactors. This hydropower expansion could also unlock the integration of a further 1.2GW of wind power into the grid.

Tajikistan

Hydropower installed capacity (2024)
5,893
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
21
TWh

Tajikistan aims to reach 100% renewable energy by 2032, with more than 90% already sourced from hydropower. The National Water Strategy, adopted in late 2024, supports climate and development goals through 2040. Meanwhile, nearly US$1 billion funding has been secured for the Rogun Hydropower Project, including loans and grants from the World Bank, AIIB, OPEC and the Islamic Development Bank. An additional US$19 million in state funding from the Government of Tajikistan has also been allocated. 

The country’s electricity exports totalled US$82.3 million in 2024 as grid upgrades continue with a €20 million EBRD grant. Modernisation of units at the Nurek and Qayroqqum (Kairakkum) hydropower projects were completed in 2024. The President announced the creation of a new oversight agency for energy. 

Russia and Tajikistan signed a cooperation agreement on the operation of the 670MW Sangtuda hydropower project, the second largest currently in operation in Tajikistan.

Tanzania

Hydropower installed capacity (2024)
2,704
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
4
TWh

East African power generation received a major boost in 2024 with the commissioning of six turbines at Tanzania’s Julius Nyerere Hydropower Plant. The 2,115MW facility on the Rufiji River comprises nine 235MW turbines and is designed to supply Tanzania, Kenya, Uganda and Zambia. The US$2.9 billion project is expected to enhance regional grid stability and cross-border electricity access.

Thailand

Hydropower installed capacity (2024)
4,569
MW
Pumped storage installed capacity (2024)
1,531
MW
Generation by hydropower (2024)
7
TWh

Thailand’s Electricity Generating Authority (EGAT) has completed a 24MW floating solar PV system at Ubol Ratana Dam in 2024, creating a hybrid solar–hydro setup. A 6MWh battery energy storage system enables smooth transitions, with solar power used during the day and hydro at night. Thailand is also negotiating hydropower imports from Laos. While no formal agreement has been signed, a deal is expected by 2025 or 2026, with exports potentially beginning in the late 2020s or early 2030s, depending on infrastructure completion. EGAT is also in the early stages of developing PSH projects in Thailand. 

Uganda

Hydropower installed capacity (2024)
2,107
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
6
TWh

Uganda has fully commissioned the 600MW Karuma hydropower project, raising national generation capacity to 2,000MW. Built by Sinohydro, the US$1.7 billion plant was largely financed through loans from the Export-Import Bank of China, which provided US$1.4 billion. Uganda is now seeking funding for three additional Nile River projects – Ayago (840MW), Kiba (400MW) and Oriang (392MW) – which will boost capacity by a further 80%.

United Kingdom

Hydropower installed capacity (2024)
4,723
MW
Pumped storage installed capacity (2024)
2,833
MW
Generation by hydropower (2024)
6
TWh

The UK Government is among those pioneering political support for long duration electricity storage across Europe. In October 2024, it instructed sector regulator Ofgem to open the first round of applications for the Cap & Floor scheme, a revenue support mechanism designed to back new long-duration electricity storage projects. The scheme, which opened in April 2025, marks a major step forward for the UK’s PSH market. Several utilities and developers are now advancing project identification and development. Coire Glas reached a milestone in December 2024 with the completion of a £100 million exploratory works programme, including the drilling of a 1.2km tunnel in the Scottish Highlands. The 1.3GW project is expected to provide 30GWh of storage – enough to power three million homes for 24 hours. Progress is also underway on the 600MW Cruachan 2 project, with suppliers and a consulting firm appointed for the construction of the underground facility near Drax’s existing plant in Scotland.

United States of America

Hydropower installed capacity (2024)
102,096
MW
Pumped storage installed capacity (2024)
22,266
MW
Generation by hydropower (2024)
242
TWh

Hydropower attracted strong federal investment in the US in 2024. For example, in February the United States Department of Energy (DOE) awarded a total of $76 million to four proposed hydropower projects – three in Alaska and one in Washington State.

This funding will have a particular impact in Alaska, where small, remote communities find it extremely challenging to raise the capital required to construct the hydropower infrastructure needed to improve system reliability and assist the transition from diesel generation to renewables.

As a further vote of confidence in hydropower, the DOE’s Water Power Technologies Office (WPTO) announced in June investments worth more than $1.7 million in 16 hydropower and 12 marine power research and development projects at the department’s laboratories.

It also announced $1 million in funding from the Bipartisan Infrastructure Law to support the Hydropower Foundation’s hydropower workforce development programmes.

Meanwhile, the DOE’s Grid Deployment Office (GDO) announced the selection of 293 hydroelectric projects across 33 states to receive more than $430 million in Maintaining and Enhancing Hydroelectricity Incentive payments.

The funding, which comes from Section 247 of the BIL, can be used to fund grid resilience, dam safety improvements and/or environmental impact reduction.

However, the incentives for hydropower and other renewable energy projects under the BIL are at risk. The new government which came into place in early 2025 took measures to restrict or eliminate key incentives put into place by the previous administration – a situation to watch as the United States hydropower sector is working hard to establish a tax credit to support critical upgrades to existing hydropower projects.

The Department of Energy’s national laboratory system has also been busy conducting research and publishing reports relevant to the hydropower industry:

  • The National Renewable Energy Laboratory (NREL) developed a detailed labour and construction cost-estimation tool for closed-loop PSH plants.
  • NREL also published a report highlighting the significant untapped potential for hydropower in the US. It asserted that the development of medium-sized hydropower and pumped storage would advance the nation’s clean energy transition.
  • Oak Ridge National Laboratory published an updated dataset revealing that 2,564 non-powered dams in the contiguous United States could theoretically generate a total of 4.1GW.
  • The Pacific Northwest National Laboratory published a study that examined how climate change could impact hydropower generation in the US. It found that generation could increase by 5% by 2039 and 10% by 2059 throughout the United States due to increases in seasonal precipitation, albeit with regional disparities.

In power plant news, Duke Energy completed the upgrade of its four-unit, 1,680MW Bad Creek PSH facility. The refurbishment added 320MW of energy storage, significantly increasing reliability for consumers.

Uruguay

Hydropower installed capacity (2024)
1,538
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
7
TWh

In 2024, Uruguay’s total electricity production climbed to a record 14.4TWh. Hydropower accounted for over 50% of that output, more than doubling its year-on-year generation and cementing its role as the country’s leading renewable source. Work also began on the modernisation of the Rincón de Baygorria hydroelectric plant during 2024, with plans to increase installed capacity to 120MW. The project is managed by Andritz in consortium with SACEEM. Uruguay’s 2024-2043 Generation Expansion Plan forecasts annual electricity demand reaching 17.8TWh by 2043, highlighting the need for new solar and wind projects as hydropower’s relative contribution continues to decline.

Uzbekistan

Hydropower installed capacity (2024)
2,382
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
8
TWh

Uzbekistan declared 2025 the “Year of Environmental Protection and Green Economy” and the Government indicated Uzbekistan has 10GW of hydropower potential and plans to reach 6GW by 2028. To support this goal, state-owned power utility Uzbekhydroenergo aims to attract US$6.5 billion to build 140 plants. Hydropower generation rose 20% in 2024, supported by the modernisation of the Naryn cascade. In July 2024, the Senate approved the Law on Electric Power industry and the ADB approved $400 million for policy reforms to the market-led power sector. 

President Mirziyoyev announced plans to increase private investment in green energy and to build nearly 3,000 micro-hydro plants which will add over 160MW by 2026, of which more than 1,000 plants will be commissioned in 2025. Zarchob-1A HPP was commissioned on the nation’s independence anniversary. 

Venezuela

Hydropower installed capacity (2024)
18,366
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
73
TWh

In recent years, Venezuela’s hydropower sector has struggled with declining capacity due to economic challenges and structural neglect of key infrastructure, such as the Guri Dam (10,200MW) and the Caroní River cascade. In response, recent efforts have been focused on restoring existing facilities. During 2024, for example, the General José Antonio Páez hydroelectric complex in Barinas was reactivated, adding 120MW to the grid. Modernisation investments are also increasing, often backed by development banks. In December 2024, the Latin American Development Bank (CAF) authorised a $380 million loan to help improve the efficiency and extend the operational life of the country’s Simón Bolívar plant. The project will cost US$610.43 million in total.

Vietnam

Hydropower installed capacity (2024)
23,058
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
96
TWh

Vietnam remains a key hydropower producer, with growing investment in PSH supported by overseas funding and a revised energy plan. The country’s Power Development Plan VIII highlights hydropower’s role in ensuring grid stability amid rising solar and wind capacity. Vietnam continues to address environmental challenges, particularly flood management and transboundary water coordination. In October 2024, India’s Adani Group announced plans to develop 10GW of overseas hydropower projects, with Vietnam identified as a key country for potential investment.  

As part of the Unified Electricity System Operator’s plans for grid modernisation through 2042, a new digital system – SPDM – has been introduced to automate hourly balancing and enhance grid reliability. RusHydro’s modernisation programme added 33.5MW of capacity in 2024 across Ust-Srednekanskaya, Ezminskaya, Nizhny Novgorod, Votkinskaya, Saratov, Volzhskaya and Cheboksary. Upgrades are also ongoing at the Uglich, Volzhskaya, Saratov and Nizhny Novgorod hydropower plants.

Zambia

Hydropower installed capacity (2024)
3,164
MW
Pumped storage installed capacity (2024)
0
MW
Generation by hydropower (2024)
11
TWh

Severe drought has reduced generation at the Kariba hydropower station, causing power cuts of up to 21 hours a day in both Zambia and Zimbabwe. While emergency measures are in place, Zambia is exploring new supply options, including raising solar to 30%, expanding hydropower in the wetter north, and controversially advancing coal projects that could worsen climate-related drought.

Countries to watch

Key

Low unexploited potential/minimal policy activity/limited project pipeline
Moderate unexploited potential/some policy activity/intermediate project pipeline
High unexploited potential/strong policy activity/Large project pipeline
Country
Unexploited potential
Policy activity
Development pipeline
Canada

Canada

Unexploited potential

Canada has a well-established hydropower fleet, but significant potential remains.

Policy activity

Its federal government and several provinces are promoting new hydropower development.

Development pipeline

Several projects are underway to increase capacity at existing plants and build new ones.

United States

United States

Unexploited potential

Approximately 80 PSH sites have been identified, most of which are closed loop.

Policy activity

The US Federal Energy Regulatory Commission (FERC) has introduced expedited licensing processes for closed-loop PSH projects, reducing permitting times from several years to months.

Development pipeline

67 new projects are in various stages of planning across 21 states, representing more than 50GW of new storage capacity. Three projects are fully permitted and awaiting final investment decisions.

Costa Rica

Costa Rica

Unexploited potential

Costa Rica has a well-established hydropower fleet, but potential remains.

Policy activity

New hydropower development is underway. The Renewable Energy Laws and Regulations Report 2025 highlights updated incentives for private renewable energy projects, streamlined permitting processes for small hydropower and storage, and favourable feed-in tariffs for run-of-river plants. 

Development pipeline

One new project announced.

Dominican Republic

Dominican Republic

Unexploited potential

The Dominican Republic has identified new greenfield and brownfield PSH sites. 

Policy activity

The country’s state-owned hydroelectric utility has called for tenders to better define the potential of PSH.

Development pipeline

The development pipeline is unclear.

Ecuador 

Ecuador 

Unexploited potential

Ecuador has tapped only 7% of its hydro power potential.

Policy activity

Government initiatives have been designed to help Ecuador meet its long-term goal of sourcing 80% of its electricity from renewable sources. Further policy efforts are under way to encourage greater private sector participation.

Development pipeline

Key projects include two new run-of-river plants, which will add approximately 150MW, and the ambitious Zamora G8 project (3,600MW), now in final feasibility. The Toachi-Pilatón complex (254MW) is also nearing completion.

Argentina 

Argentina 

Unexploited potential

Argentina has harnessed only 20% of its hydropower potential. The Inter-American Development Bank has identified 23 potential PSH projects with average installed capacities of 414.5MW.

Policy activity

Recent policy initiatives have focused on modernising ageing assets rather than launching new mega-dams. Argentina recently began recognising pumped hydro in the wholesale market, with plants remunerated for both energy generated, and energy consumed for pumping.

Development pipeline

Contract renewals have stalled the Néstor Kirchner and Jorge Cepernic dams (1,310MW). The Aña Cuá Expansion (270MW) has halted due to funding and binational tensions. Chihuido I (637MW) awaits financial closure. In PSH, Argentina’s focus has been on fully reactivating Río Grande’s capacity, with the 750MW facility operating at 50% capacity.

Chile

Chile

Unexploited potential

The country has significant potential for small and micro run-of-river projects and pumped storage. Chile has realised approximately 53% of its estimated 16GW hydropower potential. The IADB has identified 16 potential sites for PSH development.

Policy activity

Permitting has been streamlined for energy storage and integrated hybrid projects. Chile’s government announced a circa US$2 billion investment in energy storage by 2026. Energy storage assets can now earn revenue from capacity and ancillary services in Chile, improving the bankability of PSH.

Development pipeline

Four hydropower projects are under construction totalling 194.5MW, with a combined investment of $677 million. The Los Lagos Run-of-River project (52MW) has also received approval. Chile’s two biggest PSH projects – Paposo (800MW) and Espejo de Tarapacá (300MW) – have both stalled. Paposo due to environmental concerns and Espejo de Tarapacá due to funding.

Peru

Peru

Unexploited potential

Peru has harnessed 8% of its hydropower potential of 69.45GW.

Policy activity

Recent policy initiatives seek to accelerate concessions, shorten environmental review timelines, and accelerate consent processes. An additional initiative seeks to simplify access to competitive financing and shorten perfectibility and construction-licensing periods for small hydro projects.

Development pipeline

The Ministry of Mines and Energy has confirmed that six projects totalling 664MW will enter commercial operation between 2025 and 2027. These include the San Gabán III, Santa Lorenza and Anashironi hydroelectric plants, as well as the Centauro I and Centauro III facilities.

Brazil

Brazil

Unexploited potential

The IADB has identified 28 sites for potential PSH development with an average installed capacity of 387MWh. EPE's research on pumped storage in Brazil, which incorporates social and environmental factors, has identified 15 possible locations for PSH development.

Policy activity

Policy objectives are set by ANEEL, clarifying questions about adaptation to grid access, licensing regulation and remuneration. Brazil’s Mines and Energy Ministry highlighted pumped storage “reversible” plants in its 2050 energy policy plan as a preferred alternative to new mega-dams. PS is currently unable to access auctions for storage.

Development pipeline

While the signs look promising, there are no notable projects in the development pipeline yet.

Türkiye 

Türkiye 

Unexploited potential

Opportunities remain in Türkiye to develop new conventional hydropower projects and expand existing facilities

Policy activity

The government has made hydropower a central pillar of its energy policy during the past two decades, providing substantial support for the development of new facilities.

Development pipeline

A robust pipeline of conventional hydropower projects is progressing in the country, with nearly 600MW currently under construction.

Switzerland 

Switzerland 

Unexploited potential

While potential for new hydropower construction is limited in Switzerland, opportunities remain to expand storage capacity across the existing reservoir fleet.

Policy activity

A law introduced in 2023 streamlines approval processes for hydropower projects, supporting the national goal to add 2TWh of storage capacity by expanding existing infrastructure.

Development pipeline

Owners of existing facilities are obliged to assess which of their assets should be upgraded before developing plans for modernisation.

Austria

Austria

Unexploited potential

There is substantial potential to expand Austria’s existing PSH fleet.

Policy activity

The country’s National Energy and Climate Plan emphasises renewable expansion and storage integration, identifying PSH as central to achieving long-term energy goals.

Development pipeline

Austria has a strong pipeline of pumped storage projects, with approximately 1.3GW under construction and more than 2.8GW in early development stages.

United Kingdom 

United Kingdom 

Unexploited potential

Scotland and Wales have significant potential for expansion of the PSH fleet, with numerous projects recently announced.

Policy activity

The introduction of the Cap & Floor scheme, designed to support long-duration electricity storage, is helping to revitalise the PSH market by providing clearer investment signals and indicating strong political commitment.

Development pipeline

More than 13GW of pumped storage projects have been announced in the UK and are currently at various stages of development.

Spain

Spain

Unexploited potential

There is significant potential to expand Spain’s pumped storage fleet, particularly through brownfield developments connecting existing reservoirs.

Policy activity

Spain’s updated National Energy and Climate Plan has set an ambitious energy storage target of 22.5GW by 2030, up from 20GW, with pumped storage hydropower included among the key technologies.

Development pipeline

Approximately 7GW of PSH projects have been identified in Spain, although only 300MW are currently under construction.

Italy

Italy

Unexploited potential

There is noticeable potential to expand Italy’s PSH fleet, particularly through brownfield developments linking existing reservoirs.

Policy activity

Italy has introduced a new capacity mechanism (MACSE) to support the development of large-scale electricity storage solutions. National transmission operator Terna has been tasked with proposing changes to the rules governing pumped storage plant participation in the scheme.

Development pipeline

The country has a PSH pipeline with a combined potential installed capacity of nearly 4GW.

Greece

Greece 

Unexploited potential

Greece has significant potential to develop pumped storage through greenfield and brownfield projects, as well as by converting existing non-hydro infrastructure.

Policy activity

The country’s National Energy and Climate Plan sets a target of 3GW of energy storage capacity by 2030.

Development pipeline

Greece has more than 3GW of pumped storage projects in development, with approximately one third of this pipeline already under construction.

Nigeria 

Nigeria

Unexploited potential

Nigeria has considerable hydropower potential of over 14GW, especially in central and northern regions. Only about 15% of this capacity has been utilised.

Policy activity

Nigeria has launched the Sustainable Power and Irrigation Project, aiming to unlock 10,000MW of hydropower capacity by utilising existing dams and developing new projects.

Development pipeline

Nigeria has a handful of mid-to-large projects under construction, like Mambilla (3,050MW), and many in approval stages.

Democratic Republic of the Congo

Democratic Republic of the Congo

Unexploited potential

The DRC holds undeveloped hydropower reserves, notably along the Congo River. It potential of around 100GW (almost 13% of the world’s total), but less than 3% of this capacity is exploited.

Policy activity

The DRC government is taking steps to exploit more of its hydro potential, through international partnerships and regional initiatives. It aims to reform its power sector to attract further investment.

Development pipeline

Some smaller projects are in construction, but Inga III (4,800MW) is at the regulatory stage and the mega-project Grand Inga (44,000MW) is awaiting regulator approval and financing.

Mozambique

Mozambique

Unexploited potential

Mozambique has hydropower resources, particularly in the Zambezi River basin. The country’s technically feasible hydropower potential is more than 12,000MW, of which only around 20% has been exploited.

Policy activity

The government is actively pursuing large hydro expansions through public-private and regional initiatives. Policy measures, like a feed-in tariff to encourage small hydro investments, and efforts to attract foreign partners are in place to integrate new hydropower, both for domestic use and export.

Development pipeline

Mphanda Nkuwa (1,500MW) is under construction, supported by several regulator-approved mid-sized projects.

Ethiopia

Ethiopia

Unexploited potential

Ethiopia boasts economically feasible hydropower potential of approximately 45GW. The country aims to harness a significant portion of this capacity to become a major power exporter in the region.

Policy activity

Hydropower is the backbone of Ethiopia’s energy strategy with plans to become a regional electricity export hub by 2030. The government has proactively built dams for domestic supply and exports, achieving around 4.3GW hydro installed and 6.6GW under construction. It is opening the sector to independent power producers.

Development pipeline

The country has a broad and active pipeline including multiple large projects under construction, such as Koysha (1,800MW) and the Grand Ethiopian Renaissance Dam (5,150MW).

Cameroon

Cameroon

Unexploited potential

Cameroon’s economically exploitable hydropower potential is estimated around 12,600MW, with major potential in the Sanaga and Lom rivers. Only about 4% of this potential has been developed.

Policy activity

Cameroon has developed a National Water Policy and hydropower expansion is integral to its long-term development vision, Emergence 2035. The strategy is to use hydropower for energy access and become a regional power exporter, while ensuring new projects align with environmental and social standards.

Development pipeline

Multiple large-scale projects are under construction, like Nachtigal Falls (420MW) and Grand Eweng (1,800MW), with several more regulator approved.

Morocco

Morocco

Unexploited potential

Morocco already utilises PS but is expanding further. The Office National de l’Electricité et de l’Eau Potable (ONEE) has mapped out around 1,606 potential PSH sites, with over 36% deemed highly suitable.

Policy activity

The country has integrated PS into its renewable energy strategy, aiming for 52% of electricity generation from renewables by 2030. ONEE is advancing PSH projects to support its renewable energy targets.

Development pipeline

Morocco has a robust pipeline with three PSH projects totalling nearly 1,000MW, including the operational Abdelmoumen project (350MW), and two projects under construction: Ifahsa (300MW) and El Menzel (300MW).

South Africa

South Africa

Unexploited potential

The Department of Water and Sanitation has identified seven sites for potential PS schemes, aligned with coal phase-out zones.

Policy activity

South Africa supports expansion of PSH to enhance grid stability and integrate renewable energy. Eskom, the national utility company, operates existing PSH schemes and is developing other projects, a priority under the Infrastructure South Africa Programme.

Development pipeline

The 1,500MW Tubatse project has been announced with international interest.

Kyrgzystan 

Kyrgzystan 

Unexploited potential

The country’s hydropower potential is estimated at 140TWh per year, of which approximately 10% has been exploited.

Policy activity

Kyrgyzstan has been actively supporting intergovernmental agreements and regional electricity sharing initiatives related to the 1,860MW Kambarata-1 hydropower project.

Development pipeline

Four projects are currently under construction, with several others announced, including the Suusamyr–Kokomeren cascade, which is expected to add 1,305MW of capacity.

Pakistan

Pakistan

Unexploited potential

The country has 60GW of hydropower potential of which approximately 18% has been exploited.

Policy activity

Pakistan launched its ‘Decade of Dams’ initiative in 2021, aiming to expand installed hydropower capacity from approximately 9GW to 20GW by 2030.

Development pipeline

The 4,320MW Dasu and 800MW Mohmand dams are under construction. The Tarbela 5th Extension will increase the project’s installed capacity from 4,888MW to 6,418MW.

Tajikistan 

Tajikistan 

Unexploited potential

Tajikistan has the potential to generate 527TWh of electricity annually from hydropower, but only around 4% of this capacity has been developed to date.

Policy activity

Tajikistan has announced plans to achieve 100% renewable electricity by 2032, with hydropower playing a central role.

Development pipeline

The country is seeking to become a regional electricity powerhouse through the 3,600MW Rogun project and the CASA-1000 transmission network.

Bhutan 

Bhutan 

Unexploited potential

Bhutan has an estimated 35GW of hydropower potential, of which approximately 9% has been developed. In July 2024, the first two turbine generators of the 1,020MW Punatsangchhu II project became operational.

Policy activity

In August 2024, Bhutan’s Electricity Regulatory Authority released its Strategic Plan 2024-2029, aimed at strengthening regulatory frameworks and promoting innovation across the power sector. The country has also signed agreements with several regional governments to support its growing hydropower pipeline.

Development pipeline

The 1,200MW Punatsangchhu-I is nearing completion as well as several other projects under construction. The 2,584MW Sankosh project has been announced.

India 

India 

Unexploited potential

With an estimated technical potential of up to 181.5GW across both on-river and off-river sites, PSH is recognised in India as a mature, proven solution for large-scale energy storage, grid stability and peak demand management.

Policy activity

The Indian government has developed national and state-level policies to support pumped storage hydropower (PSH), including the PSP Guidelines and the Hydropower Policy 2025. Policy momentum remains strong, with new measures such as the Energy Storage Obligation, waivers on interstate transmission charges and proposed viability gap funding to incentivise PSH deployment.

Development pipeline

Several projects are nearing completion that will nearly double India’s installed capacity from 4.7GW to 8GW.

Iran

Iran

Unexploited potential

Iran operates the 1,040MW Siah Bisheh pumped storage plant and is progressing with development of the Azad pumped storage project.

Policy activity

Iran’s Minister of Energy, Dr Abbas Aliabadi, has called for the accelerated implementation of pumped storage projects, although limited policy progress has been made to date.

Development pipeline

Iran’s 510MW Azad pumped storage project is planned for completion in 2027.

Laos 

Laos 

Unexploited potential

Laos holds a vast reserve of undeveloped hydropower capacity, enabling a policy to become a key regional electricity exporter and the "Battery of Southeast Asia".

Policy activity

This country has implemented policies like the Sustainable Hydropower Development Policy and Renewable Energy Strategy with the aim of becoming a key regional energy supplier, targeting electricity exports of up to 14,800MW by 2025.

Development pipeline

It is actively expanding its hydropower sector, with more than 4,000MW of new projects currently under construction. Key projects include the 1,400MW Luang Prabang Dam, the 728MW Phou Ngoy Dam, and the 1,060MW Pak Beng Dam, all located on the Mekong River.

China 

China 

Unexploited potential

China continues to expand its conventional hydropower capacity and is aggressively expanding its pumped storage hydropower capacity.

Policy activity

China’s latest energy policy strategies set out plans for expansion. The 13th Five-Year Plan for the electricity sector outlines plans to add 60GW of new conventional hydropower capacity.

Development pipeline

The country has a significant pipeline of projects underway, with large-scale conventional projects in major river basins such as the Jinsha, Dadu, and Yalong Rivers. There are more than 200 PSH projects in the pipeline backed by substantial funding, streamlined permitting, and supportive market reforms to accelerate implementation.

Indonesia

Indonesia 

Unexploited potential

Indonesia has completed a comprehensive survey of potential sites and identified the most favourable locations.

Policy activity

This country is committed to the expansion of hydropower capacity. The updated Electricity Supply Business Plan (RUPTL) for 2025–2034 targets a 35% renewable energy share by 2034, with 16GW of new hydropower capacity.

Development pipeline

There are notable projects in the development pipeline. In 2025 alone, the Upper Cisokan Pumped Storage Plant (1,040 MW) and conventional projects at Jatigede (110 MW), Asahan 3 (174 MW), Peusangan 1 and 2 (88 MW) and Merangin (350 MW) are due online.

Malaysia 

Malaysia 

Unexploited potential

Malaysia still holds significant potential. While large projects continue, Malaysia is shifting toward small hydropower (SHP) and hybrid hydro-solar initiatives.

Policy activity

Malaysia’s National Energy Policy (2022–2040) designates hydroelectric power as a key technology for renewable energy development. The government aims to achieve 31% renewable energy capacity by 2025 and 40% by 2035, with hydropower playing a significant role in meeting these targets.

Development pipeline

Malaysia has a number of projects at various stages of the development pipeline. These include major projects like the 1,285MW Baleh plant in Sarawak, expected by 2029/30, and the 300MW Nenggiri plant in Kelantan, slated for 2027.

Vietnam

Vietnam

Unexploited potential

Vietnam has considerable untapped hydro resources due to its abundant river systems and mountainous terrain.

Policy activity

Vietnam’s Power Development Plan VIII, initially approved in May 2023, underscores strong government support for hydropower, prioritising both traditional and pumped storage projects to enhance energy security and promote clean, sustainable growth.

Development pipeline

Vietnam is actively developing its pumped storage hydropower capacity, with the 1,200MW Bac Ai Pumped Storage Plant currently under construction. Several other pumped storage projects are in the feasibility study phase.

Australia

Australia

Unexploited potential

Australia has identified significant PSH potential across multiple states, especially in areas transitioning from coal.

Policy activity

The country is making proactive moves toward PSH and long-duration energy storage (LDES), supported by strong government backing, although it does not recognise LDES or PSH in its net zero policy wording.

Development pipeline

It has a significant volume of PSH projects at various stages of the development pipeline, from detailed planning (Oven Mountain, Phoenix, Lake Lyell, Borumba) through procurement (Capricornia), to active construction (Snowy 2.0, Muswellbrook).

Philippines

Philippines

Unexploited potential

The Philippines has considerable hydro and PSH potential, with strong demand for grid stabilisation.

Policy activity

The country has proactively moved on its PSH expansion strategy, with an oversubscribed auction. The Philippine Department of Energy set a 4,250MW target for PSH in the 2025 Green Energy Auction, which drew bids of 7GW.

Development pipeline

A number of pumped storage projects are currently in the early stages of development. A total of 11 major energy projects (~4,500MW) received DOE endorsement for grid impact studies in February 2025, with PSH projects constituting the bulk of this capacity.

Case Study

Hidroituango also referred to as Ituango, is a hydropower plant located in Antioquia, Colombia, which will provide 17 per cent of the country’s electricity demand when completed in 2024. Ituango is a project of the Ituango Hydrolectric Company, made up of the majority partners Instituto para el Desarollo de Antioquia, the Government of Antioquia and Empresas Públicas de Medellín who is the main contractor and operator.

The project’s completion had been delayed due to severe weather conditions. Between April and May in 2018, Antioquia experienced heavy rains which caused large landslides. These events coupled with geological characteristics, resulted in the premature filling of the reservoir. A sudden unblocking of one of the diversion tunnels caused flooding downstream of the dam and an evacuation of the surrounding communities.  

A year later, Colombia’s National Disaster Risk Management Unit declared that the 600 families that were evacuated could safely return to their homes.  In 2021, a report warned that the decision to abort the project would pose a greater socio-environmental threat than finishing it. The Colombian licensing authority ANLA provided a series of recommendations for the safe completion of the dam and powerhouse. These recommendations were implemented and since late 2022, Ituango has been supplying continuous electricity from 600 MW capacity to the national grid.  

The project is undergoing an assessment under the Hydropower Sustainability Standard to certify its compliance and demonstrate its alignment with performance standards. This assessment is undergoing public consultation with an expected completion in June 2023.  

Once Ituango is fully completed in 2024, it will have a total installed capacity of 2,400 MW and will represent a reduction in emissions of 4.4 million tons of CO2 per year.

Interesting Fact  

Pumped storage remains largely untapped in Latin America, but a 2024 IADB report highlights its potential to boost renewable integration as ageing hydro plants modernise. The two-stage study identifies 179 possible sites across 11 countries and lays out plans for a pilot project in Pisagua, Tarapacá, Chile, providing 640MW with 12 hours of storage. The pilot uses two 4.5Mm³ reservoirs, four 160MW Francis turbines, and two 220kV lines. The US$570 million project would be constructed over 48 months at a cost of US$32/MWh and a 12.8% IRR. A proposed 1,200MW solar PV plant would add 300MW of capacity.

Find out more about Frankie

Privacy Policy